United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in the USA (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,122 MW
Active in queue1,122 MW5 requests
Agreement signed362 MW3 requests
Withdrawn7224.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J732, Douglas County
Gas
562 MWUnder construction Douglas, WIMISO Jun 2017target 2023
Gas project IA-PNM-2017-14, San Juan County
Gas
236 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Gas project 54, Grays Harbor County
Gas
199 MWPaused / redesign Grays Harbor, WAWest Dec 2017target 2026
Three Rivers Energy Center
Gas
103 MWAgreement signed Grundy, ILPJM Jul 20172023
Gas project 332, Shelby County
Gas
23.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)