United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Wyoming (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown131,933 MW
Active in queue1,933 MW13 requests
Agreement signed250 MW1 requests
Withdrawn112,681 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project PIS089, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest Oct 2024target 2028
Battery storage project S0026, Converse County
Battery storage
350 MWIn study Converse, WYWest Feb 2024target 2026
Battery storage project S0028, Converse County
Battery storage
320 MWIn study Converse, WYWest Feb 2024target 2026
Onshore wind project GI-TC-2024-15, Laramie County
Onshore wind
250 MWAgreement signed Laramie, WYWest May 2024target 2029
Other project CLPT G29, Laramie County
Other
150 MWIn study Laramie, WYWest May 2024target 2027
Gas project CLPT G30, Laramie County
Gas Β· Black Hills Electric Generation, LLC
115 MWIn study Laramie, WYWest May 2024target 2029
Gas project CLPT G31, Laramie County
Gas Β· Cheyenne Light, Fuel & Power
115 MWIn study Laramie, WYWest May 2024target 2029
Battery storage project S0025, Natrona County
Battery storage
100 MWIn study Natrona, WYWest Feb 2024target 2026
Onshore wind project PIS051, Converse County
Onshore wind Β· PacifiCorp
42.0 MWIn study Converse, WYWest Feb 2024target 2024
Onshore wind project PIS052, Carbon County
Onshore wind Β· PacifiCorp
30.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project PIS053, Carbon County
Onshore wind Β· PacifiCorp
28.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project PIS050, Carbon County
Onshore wind Β· PacifiCorp
26.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project PIS054, Carbon County
Onshore wind Β· PacifiCorp
6.6 MWIn study Carbon, WYWest Feb 2024target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)