Interconnection queue in Wyoming (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown235,354 MW
Active in queue5,354 MW23 requests
Agreement signed2,716 MW15 requests
Withdrawn298,829 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 661, Sweetwater County
Solar + storage Β· Sawtooth DevCo, LLC
1,000 MWPaused / redesign Sweetwater, WYWest Jun 2022target 2027
Nuclear project C2-32, Lincoln County
Nuclear Β· US SFR Owner, LLC
500 MWAgreement signed Lincoln, WYWest Apr 2022target 2031
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Solar + storage project CLPT G21, Laramie County
Solar + storage
400 MWAgreement signed Laramie, WYWest Sep 2022target 2025
Solar + storage project CLPT G20, Laramie County
Solar + storage
365 MWAgreement signed Laramie, WYWest Jul 2022target 2025
Other project CLPT G17, Laramie County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Other project CLPT G16, Platte County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Platte, WYWest Apr 2022target 2025
Solar project CLPT G18, Converse County
Solar Β· DUTC bn, LLC
255 MWAgreement signed Converse, WYWest Jun 2022target 2024
Solar project S0006, Carbon County
Solar Β· PacifiCorp
250 MWIn study Carbon, WYWest Mar 2022target 2026
Solar project S0005, Carbon County
Solar Β· PacifiCorp
250 MWIn study Carbon, WYWest Mar 2022target 2026
Solar project S0004, Carbon County
Solar Β· PacifiCorp
240 MWIn study Carbon, WYWest Mar 2022target 2026
Solar project S0003, Converse County
Solar Β· PacifiCorp
237 MWIn study Converse, WYWest Mar 2022target 2026
Onshore wind project BHBE G17, Campbell County
Onshore wind
200 MWAgreement signed Campbell, WYWest Mar 2022target 2026
Onshore wind project C2-49, Converse County
Onshore wind
150 MWIn study Converse, WYWest May 2022target 2026
Gas project CLPT G22, Laramie County
Gas Β· Black Hills Electric Generation, LLC
115 MWAgreement signed Laramie, WYWest Nov 2022target 2024
Solar project S0002, Carbon County
Solar Β· PacifiCorp
111 MWIn study Carbon, WYWest Mar 2022target 2025
Onshore wind project BHBE G18, Campbell County
Onshore wind
100 MWAgreement signed Campbell, WYWest Mar 2022target 2027
Gas project C2-48, Lincoln County
Gas Β· PacifiCorp
48.0 MWAgreement signed Lincoln, WYWest May 2022target 2031
Onshore wind project C2-12, Converse County
Onshore wind Β· PacifiCorp
42.0 MWAgreement signed Converse, WYWest Apr 2022target 2036
Onshore wind project C2-13, Carbon County
Onshore wind Β· PacifiCorp
30.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project C2-14, Carbon County
Onshore wind Β· PacifiCorp
28.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project C2-11, Carbon County
Onshore wind Β· PacifiCorp
26.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project C2-15, Carbon County
Onshore wind Β· PacifiCorp
6.6 MWAgreement signed Carbon, WYWest Apr 2022target 2036

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)