Onshore wind interconnection queue in Wyoming

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown315,445 MW
Active in queue5,445 MW31 requests
Agreement signed2,743 MW15 requests
Withdrawn14938.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project C1-35, Carbon County
Onshore wind Β· Lucky Star Wind, LLC
500 MWAgreement signed Carbon, WYWest May 2021target 2028
Onshore wind project T2-057, Carbon County
Onshore wind
400 MWIn study Carbon, WYWest Sep 2025target 2029
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Onshore wind project GI-TC-2024-16, Laramie County
Onshore wind
400 MWAgreement signed Laramie, WYWest May 2023target 2029
Onshore wind project PIS089, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest Oct 2024target 2028
Onshore wind project 836, Carbon County
Onshore wind Β· PacifiCorp
400 MWAgreement signed Carbon, WYWest Dec 2016target 2027
Onshore wind project 21-08242, Laramie County
Onshore wind
350 MWIn study Laramie, WYWest Aug 2021target 2025
Onshore wind project BHBE G16, Campbell County
Onshore wind
290 MWAgreement signed Campbell, WYWest Dec 2021target 2024
Onshore wind project 719, Albany County
Onshore wind Β· Two Rivers Wind, LLC
280 MWPaused / redesign Albany, WYWest Nov 2015target 2024
Onshore wind project GI-TC-2024-15, Laramie County
Onshore wind
250 MWAgreement signed Laramie, WYWest May 2024target 2029
Onshore wind project BHBE G17, Campbell County
Onshore wind
200 MWAgreement signed Campbell, WYWest Mar 2022target 2026
Onshore wind project CLPT G24, Laramie County
Onshore wind
200 MWAgreement signed Laramie, WYWest Feb 2023target 2026
Onshore wind project CLPT G23, Laramie County
Onshore wind
150 MWAgreement signed Laramie, WYWest Feb 2023target 2026
Onshore wind project C2-49, Converse County
Onshore wind
150 MWIn study Converse, WYWest May 2022target 2026
Onshore wind project GI-TC-2024-05, Platte County
Onshore wind
150 MWIn study Platte, WYWest May 2023target 2026
Onshore wind project GI-TC-2024-06, Platte County
Onshore wind
150 MWIn study Platte, WYWest May 2023target 2026
Onshore wind project GI-TC-2024-04, Platte County
Onshore wind
150 MWIn study Platte, WYWest May 2023target 2026
Onshore wind project 715, Uinta County
Onshore wind Β· Uinta Wind Energy, LLC
120 MWAgreement signed Uinta, WYWest Oct 2015target 2025
Onshore wind project BHBE G18, Campbell County
Onshore wind
100 MWAgreement signed Campbell, WYWest Mar 2022target 2027
Onshore wind project S0024, Fort Bridger County
Onshore wind
79.5 MWIn study Fort Bridger, WYWest Nov 2023target 2027
Onshore wind project S0023, Fort Bridger County
Onshore wind
60.0 MWIn study Fort Bridger, WYWest Nov 2023target 2027
Onshore wind project C2-12, Converse County
Onshore wind Β· PacifiCorp
42.0 MWAgreement signed Converse, WYWest Apr 2022target 2036
Onshore wind project PIS051, Converse County
Onshore wind Β· PacifiCorp
42.0 MWIn study Converse, WYWest Feb 2024target 2024
Onshore wind project C2-13, Carbon County
Onshore wind Β· PacifiCorp
30.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project PIS052, Carbon County
Onshore wind Β· PacifiCorp
30.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project C2-14, Carbon County
Onshore wind Β· PacifiCorp
28.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project PIS053, Carbon County
Onshore wind Β· PacifiCorp
28.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project C2-11, Carbon County
Onshore wind Β· PacifiCorp
26.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project PIS050, Carbon County
Onshore wind Β· PacifiCorp
26.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project PIS054, Carbon County
Onshore wind Β· PacifiCorp
6.6 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project C2-15, Carbon County
Onshore wind Β· PacifiCorp
6.6 MWAgreement signed Carbon, WYWest Apr 2022target 2036

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)