Withdrawn queue requests in Wyoming (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown298,829 MW
Active in queue5,354 MW23 requests
Agreement signed2,716 MW15 requests
Withdrawn298,829 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

29 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project C2-46, Laramie County
Onshore wind
600 MWWithdrawn / abandoned Laramie, WYWest Apr 2022target 2025
Onshore wind project C2-43, Sweetwater County
Onshore wind
600 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2022target 2025
Onshore wind project C2-104, Lincoln County
Onshore wind
600 MWWithdrawn / abandoned Lincoln, WYWest May 2022target 2025
Onshore wind project C2-34, Carbon County
Onshore wind
506 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2024
Onshore wind project C2-108, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Onshore wind project C2-107, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Battery storage project C2-25, Lincoln County
Battery storage Β· PacifiCorp
500 MWWithdrawn / abandoned Lincoln, WYWest Apr 2022target 2028
Battery storage project C2-17, Converse County
Battery storage Β· PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Battery storage project C2-23, Converse County
Battery storage Β· PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Onshore wind project PIS004, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2025
Onshore wind project C2-105, Lincoln County
Onshore wind
300 MWWithdrawn / abandoned Lincoln, WYWest May 2022target 2025
Solar + storage project C2-38, Sweetwater County
Solar + storage
300 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2022target 2025
Onshore wind project C2-63, Uinta County
Onshore wind
220 MWWithdrawn / abandoned Uinta, WYWest May 2022target 2026
Battery storage project C2-01, Sweetwater County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2022target 2026
Battery storage project PIS010, Carbon County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Carbon, WYWest Jun 2022target 2026
Onshore wind project C2-53, Campbell County
Onshore wind
200 MWWithdrawn / abandoned Campbell, WYWest May 2022target 2025
Battery storage project PIS008, Sweetwater County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Sweetwater, WYWest Jun 2022target 2026
Battery storage project C2-03, Carbon County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2026
Solar + storage project C2-118, Natrona County
Solar + storage
199 MWWithdrawn / abandoned Natrona, WYWest May 2022target 2026
Solar + storage project C2-116, Carbon County
Solar + storage
199 MWWithdrawn / abandoned Carbon, WYWest May 2022target 2026
Solar project C2-111, Natrona County
Solar
199 MWWithdrawn / abandoned Natrona, WYWest May 2022target 2025
Solar + storage project C2-52, Natrona County
Solar + storage
176 MWWithdrawn / abandoned Natrona, WYWest May 2022target 2025
Solar + storage project C2-47, Laramie County
Solar + storage
160 MWWithdrawn / abandoned Laramie, WYWest Apr 2022target 2025
Solar + storage project C2-139, Sweetwater County
Solar + storage
150 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2026
Battery storage project C2-55, Lincoln County
Battery storage
150 MWWithdrawn / abandoned Lincoln, WYWest May 2022target 2024
Solar project CLPT G19, Laramie County
Solar Β· Cheyenne Light, Fuel & Power
150 MWWithdrawn / abandoned Laramie, WYWest Jul 2022target 2025
Gas project 22-06271, Laramie County
Gas
120 MWWithdrawn / abandoned Laramie, WYWest Jun 2022target 2027
Solar + storage project C2-155, Uinta County
Solar + storage
110 MWWithdrawn / abandoned Uinta, WYWest May 2022target 2026
Onshore wind project C2-143, Uinta County
Onshore wind
90.0 MWWithdrawn / abandoned Uinta, WYWest May 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)