Battery storage project PIS010, Carbon County

Battery storage project PIS010, Carbon County is a 200 MW battery storage request withdrawn in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
PIS010
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp
Connection point (POI)
Aeolus substation
Location
Carbon County, Wyoming
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
24 June 2022
Proposed online date
December 2026

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.