United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Wisconsin (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,320 MW
Active in queue2,737 MW11 requests
Agreement signed0.0 MW0 requests
Withdrawn51,320 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3330, Kenosha County
Gas
705 MWWithdrawn / abandoned Kenosha, WIMISO Apr 2024target 2028
Battery storage project J2211, Brown County
Battery storage
200 MWWithdrawn / abandoned Brown, WIMISO Sep 2024target 2024
Onshore wind project J3332, Calumet County
Onshore wind
150 MWWithdrawn / abandoned Calumet, WIMISO Apr 2024target 2028
Solar project J3476, St. Croix County
Solar
150 MWWithdrawn / abandoned St. Croix, WIMISO Apr 2024target 2028
Solar project J3433, Barron County
Solar
115 MWWithdrawn / abandoned Barron, WIMISO Apr 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)