United States β€Ί Grid β€Ί Interconnection queues β€Ί West Virginia

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West Virginia (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown41,505 MW
Active in queue1,505 MW4 requests
Agreement signed45.0 MW1 requests
Withdrawn5808 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Maidsville CCGT
Gas
1,270 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Brandonville Solar
Solar
99.6 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Raleigh Solar Project
Solar
90.0 MWPaused / redesign Raleigh, WVPJM Sep 2018target 2025
Glen Falls Facility
Gas
45.0 MWAgreement signed Harrison, WVPJM Mar 2018target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)