OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Virginia (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,270 MW
Active in queue1,270 MW12 requests
Agreement signed855 MW8 requests
Withdrawn612,596 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
Spring Grove Solar II
Solar
150 MWAgreement signed Surry, VAPJM Jun 2017target 2025
Wild Indigo Solar
Solar
150 MWPaused / redesign Surry, VAPJM Oct 2017target 2026
Red Brick Solar
Solar
130 MWAgreement signed Lunenburg, VAPJM Dec 2017target 2026
Cartersville Solar
Solar
99.9 MWPaused / redesign Powhatan, VAPJM Mar 2017target 2026
Firefly Solar
Solar
96.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Firefly Solar
Solar
95.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Windsor PVI
Solar
85.0 MWPaused / redesign Isle Of Wight, VAPJM Mar 2017target 2023
Seven Bridges Solar
Solar
80.0 MWPaused / redesign Mecklenburg, VAPJM Sep 2017target 2026
Sweet Sue Solar
Solar
74.0 MWAgreement signed King William, VAPJM Sep 2017target 2026
Greenwood Solar
Solar
50.0 MWAgreement signed Culpeper, VAPJM Sep 2017target 2027
Walnut Solar I
Solar
20.0 MWAgreement signed King And Queen, VAPJM Mar 2017target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)