United States βΊ Grid βΊ Interconnection queues βΊ Virginia
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Virginia (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project W1-073, Caroline County Gas |
612 MW | Withdrawn / abandoned |
| Gas project W1-074, Fauquier County Gas |
610 MW | Withdrawn / abandoned |
| Offshore wind project W3-043, City Of Virginia Beach County Offshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project W3-054A, Accomack County Onshore wind |
95.0 MW | Withdrawn / abandoned |
| Onshore wind project W3-021, Pulaski County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Central Solar Park Onshore wind |
45.0 MW | Withdrawn / abandoned |
| Solar project V4-064, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-007, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-037 Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-008, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-009, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Gas project W2-009, City Of Hopewell County Gas |
18.0 MW | Withdrawn / abandoned |
| Solar project W4-001, Halifax County Solar |
7.0 MW | Withdrawn / abandoned |
| Other project W3-010, Montgomery County Other |
0.3 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)