Queue requests in study in Virginia (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown103,688 MW
Active in queue6,737 MW37 requests
Agreement signed3,049 MW27 requests
Withdrawn617,607 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Cvow 2, Oss 2 β€šΓ„Γ¬ T2G07
Offshore wind Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
836 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 1, Oss 1 - T1L11
Offshore wind Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
833 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 3, Oss 3 β€šΓ„Γ¬ T3G15
Offshore wind Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
820 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Chesterfield CT Units 1 and 2
Gas Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Axton Solar
Solar
201 MWPaused / redesign Henry, VAPJM Mar 2019target 2025
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Yadkins Energy Center
Battery storage Β· Yadkins Energy Center, LLC
100 MWIn study City Of Chesapeake, VAPJM Mar 2019target 2021
Rocky Ford Solar Energy Center
Solar
90.0 MWPaused / redesign Henry, VAPJM Mar 2019target 2026
Switchgrass Solar 1
Solar
49.0 MWPaused / redesign Accomack, VAPJM Mar 2019target 2025
Amelia Energy Facility
Solar Β· Amelia Energy Facility, LLC
41.0 MWIn study Amelia, VAPJM Sep 2019target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)