Withdrawn queue requests in Utah (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown444,653 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn444,653 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

44 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q64, Beaver County
Solar + storage ยท Intermountain Power Agency
400 MWWithdrawn / abandoned Beaver, UTWest Mar 2018target 2020
Solar + storage project 1070, Utah County
Solar + storage
400 MWWithdrawn / abandoned Utah, UTWest Sep 2018target 2021
Solar project 1049, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar project 1050, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar + storage project 1027, Tooele County
Solar + storage
251 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2022
Solar + storage project 1028, Tooele County
Solar + storage
251 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2022
Battery storage project 1038, Utah County
Battery storage
200 MWWithdrawn / abandoned Utah, UTWest Jun 2018target 2021
Solar + storage project 1092, Millard County
Solar + storage
200 MWWithdrawn / abandoned Millard, UTWest Dec 2018target 2020
Solar + storage project TCS-21, Millard County
Solar + storage
200 MWWithdrawn / abandoned Millard, UTWest Dec 2018target 2023
Solar + storage project 1073, Juab County
Solar + storage
160 MWWithdrawn / abandoned Juab, UTWest Oct 2018target 2021
Solar + storage project 1074, Utah County
Solar + storage
160 MWWithdrawn / abandoned Utah, UTWest Oct 2018target 2021
Solar project 1000, Weber County
Solar
120 MWWithdrawn / abandoned Weber, UTWest Jan 2018target 2020
Solar + storage project 1036, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jun 2018target 2021
Solar + storage project 1035, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jun 2018target 2021
Solar + storage project 1056, Juab County
Solar + storage
100 MWWithdrawn / abandoned Juab, UTWest Aug 2018target 2021
Solar + storage project 1052, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2021
Solar + storage project 1051, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2021
Solar + storage project 1024, Cache County
Solar + storage
100 MWWithdrawn / abandoned Cache, UTWest May 2018target 2020
Solar + storage project TCS-17, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Nov 2018target 2023
Solar project 1086, Tooele County
Solar
80.0 MWWithdrawn / abandoned Tooele, UTWest Nov 2018target 2021
Solar + storage project 1083, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Nov 2018target 2023
Solar + storage project TCS-22, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Dec 2018target 2022
Solar + storage project 1094, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Dec 2018target 2023
Solar project 1006, Carbon County
Solar
60.0 MWWithdrawn / abandoned Carbon, UTWest Mar 2018target 2019
Solar project 998, Tooele County
Solar
60.0 MWWithdrawn / abandoned Tooele, UTWest Jan 2018target 2021
Solar project 999, Tooele County
Solar
50.0 MWWithdrawn / abandoned Tooele, UTWest Jan 2018target 2019
Solar project 1023, Tooele County
Solar
50.0 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2020
Solar project 1048, Utah County
Solar
50.0 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Onshore wind project 1005, Summit County
Onshore wind
50.0 MWWithdrawn / abandoned Summit, UTWest Feb 2018target 2020
Solar project 1047, Utah County
Solar
50.0 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar + storage project 1053, Millard County
Solar + storage
50.0 MWWithdrawn / abandoned Millard, UTWest Jul 2018target 2020
Solar project 1037, Iron County
Solar
35.0 MWWithdrawn / abandoned Iron, UTWest Jun 2018target 2021
Solar project TCS-10, Box Elder County
Solar
32.8 MWWithdrawn / abandoned Box Elder, UTWest Mar 2018target 2023
Solar project 1010, Box Elder County
Solar
32.8 MWWithdrawn / abandoned Box Elder, UTWest Mar 2018target 2023
Solar project 1009, Tooele County
Solar
31.5 MWWithdrawn / abandoned Tooele, UTWest Mar 2018target 2019
Onshore wind project 1046, Rich County
Onshore wind
31.1 MWWithdrawn / abandoned Rich, UTWest Jul 2018target 2020
Solar project 1054, Millard County
Solar
30.0 MWWithdrawn / abandoned Millard, UTWest Jul 2018target 2020
Solar project 1039, Cache County
Solar
30.0 MWWithdrawn / abandoned Cache, UTWest Jun 2018target 2020
Solar project 1021, Box Elder County
Solar
25.0 MWWithdrawn / abandoned Box Elder, UTWest May 2018target 2020
Solar project 1004, Box Elder County
Solar
25.0 MWWithdrawn / abandoned Box Elder, UTWest Feb 2018target 2019
Solar project 1003, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest Feb 2018target 2019
Solar project 1096, Box Elder County
Solar
3.9 MWWithdrawn / abandoned Box Elder, UTWest Dec 2018target 2019
Solar project TCS-24, Box Elder County
Solar
3.9 MWWithdrawn / abandoned Box Elder, UTWest Dec 2018target 2019
Solar project 1026, Salt Lake County
Solar
0.4 MWWithdrawn / abandoned Salt Lake, UTWest May 2018target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)