United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Texas (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown162,703 MW
Active in queue10.1 GW49 requests
Agreement signed7,413 MW33 requests
Withdrawn9217.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Green Holly Solar
Solar Β· Copenhagen Infrastructure Partners Fund IV
414 MWPaused / redesign Dawson, TXERCOT Jul 2018target 2026
Arroyo Del Bisonte Solar
Solar Β· Sunchase Power
300 MWPaused / redesign Wharton, TXERCOT May 2018target 2021
Pierce Wind
Onshore wind
300 MWPaused / redesign Wharton, TXERCOT Jan 2018
Shifting Gale Wind
Onshore wind
289 MWPaused / redesign Castro, TXERCOT Apr 2018target 2025
Gulf Wind 2
Onshore wind
227 MWPaused / redesign Kenedy, TXERCOT Jan 2018
Walleye Solar
Solar Β· Sandow Lakes Ranch Solar II, LLC
215 MWIn study Milam, TXERCOT Jul 2018target 2027
Rueter Solar
Solar
200 MWPaused / redesign Bosque, TXERCOT Sep 2018
Desert Rose Solar
Solar
200 MWPaused / redesign Andrews, TXERCOT Jun 2018
CAROL wind
Onshore wind
165 MWPaused / redesign Potter, TXERCOT Dec 2018target 2024
Wang Solar SLF
Solar + storage Β· BT Yixin Solar, LLC
145 MWIn study Falls, TXERCOT Jun 2018target 2026
Tyson Nick Solar
Solar Β· Tyson Nick Solar Project, LLC
90.0 MWPaused / redesign Lamar, TXERCOT Dec 20182025
R Massengale
Gas
58.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
SP TX-12B Phase III
Solar Β· ConEd Development
40.0 MWIn study Upton, TXERCOT Sep 2018target 2025
Half Moon Battery
Battery storage
30.2 MWPaused / redesign Hidalgo, TXERCOT Sep 2018
Brandon
Gas
21.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Blue Summit repower
Onshore wind
9.9 MWPaused / redesign Wilbarger, TXERCOT Jan 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)