United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Battery storage interconnection queue in Tennessee

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6747 MW
Active in queue747 MW6 requests
Agreement signed22.0 MW1 requests
Withdrawn181,968 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 587, Hawkins County
Battery storage
225 MWIn study Hawkins, TNSoutheast Oct 2023target 2029
Battery storage project 661, Shelby County
Battery storage
200 MWIn study Shelby, TNSoutheast Oct 2024target 2026
Battery storage project 547, Roane County
Battery storage
100 MWIn study Roane, TNSoutheast Apr 2023target 2026
Battery storage project 643, Shelby County
Battery storage
100 MWIn study Shelby, TNSoutheast Sep 2024target 2027
Battery storage project 25RSC-007, Mcnairy County
Battery storage
100 MWIn study Mcnairy, TNSoutheast Jul 2025target 2030
Battery storage project 461, Loudon County
Battery storage
22.0 MWAgreement signed Loudon, TNSoutheast Nov 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)