United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Tennessee (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,269 MW
Active in queue3,530 MW5 requests
Agreement signed241 MW3 requests
Withdrawn121,269 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 477, Hardeman County
Solar + storage
200 MWWithdrawn / abandoned Hardeman, TNSoutheast Jun 2021target 2024
Solar + storage project 493, Van Buren County
Solar + storage
200 MWWithdrawn / abandoned Van Buren, TNSoutheast Jul 2021
Solar + storage project 474, Obion County
Solar + storage
180 MWWithdrawn / abandoned Obion, TNSoutheast Apr 2021
Solar project 478, Bledsoe County
Solar
155 MWWithdrawn / abandoned Bledsoe, TNSoutheast Sep 2021
Solar + storage project 494, Rhea County
Solar + storage
150 MWWithdrawn / abandoned Rhea, TNSoutheast Apr 2021
Solar + storage project 485, Bedford County
Solar + storage
130 MWWithdrawn / abandoned Bedford, TNSoutheast Oct 2021target 2024
Battery storage project 497, Jefferson County
Battery storage
100 MWWithdrawn / abandoned Jefferson, TNSoutheast Oct 2021
Solar project 481, Fayette County
Solar
60.0 MWWithdrawn / abandoned Fayette, TNSoutheast Oct 2021target 2024
Solar project 468, Franklin County
Solar
53.0 MWWithdrawn / abandoned Franklin, TNSoutheast Feb 2021
Solar project AH1-534, Greene County
Solar
22.7 MWWithdrawn / abandoned Greene, TNPJM Sep 2021target 2025
Nuclear project 470, Hamilton County
Nuclear
9.0 MWWithdrawn / abandoned Hamilton, TNSoutheast Mar 2021target 2022
Solar + storage project 473, Lake County
Solar + storage
9.0 MWWithdrawn / abandoned Lake, TNSoutheast Apr 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)