United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in South Dakota (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,283 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn71,283 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1621, Mcpherson County
Onshore wind
400 MWWithdrawn / abandoned Mcpherson, SDMISO Jun 2020target 2023
Onshore wind project GEN-2020-018, Sully County
Onshore wind
205 MWWithdrawn / abandoned Sully, SDSPP Apr 2020target 2026
Onshore wind project J1594, Clark County
Onshore wind
200 MWWithdrawn / abandoned Clark, SDMISO Jun 2020target 2023
Onshore wind project J1521, Day County
Onshore wind
200 MWWithdrawn / abandoned Day, SDMISO Jun 2020target 2022
Solar project GEN-2020-093, Potter County
Solar
150 MWWithdrawn / abandoned Potter, SDSPP Apr 2020target 2026
Onshore wind project GEN-2020-019, Tripp County
Onshore wind
108 MWWithdrawn / abandoned Tripp, SDSPP Apr 2020target 2027
Solar + storage project J1738, Mcpherson County
Solar + storage
20.0 MWWithdrawn / abandoned Mcpherson, SDMISO Jun 2020target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)