Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1066.6 MW
Active in queue66.6 MW10 requests
Agreement signed0.0 MW0 requests
Withdrawn1924,837 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-063, Beaver County
Solar
20.0 MWIn study Beaver, PAPJM Dec 2021target 2023
Solar project AH2-064, Beaver County
Solar
10.0 MWIn study Beaver, PAPJM Dec 2021target 2023
Solar project AH2-062, Chester County
Solar
5.0 MWIn study Chester, PAPJM Dec 2021target 2023
Solar project AH2-036, Bradford County
Solar
5.0 MWIn study Bradford, PAPJM Nov 2021target 2023
Solar project AH2-014, Erie County
Solar
5.0 MWIn study Erie, PAPJM Oct 2021target 2024
Solar project AH2-023, Mercer County
Solar
5.0 MWIn study Mercer, PAPJM Oct 2021target 2024
Solar project AH2-044, Clearfield County
Solar
5.0 MWIn study Clearfield, PAPJM Nov 2021target 2024
Solar project AH2-037, Fulton County
Solar
5.0 MWIn study Fulton, PAPJM Nov 2021target 2023
Other project AH2-001, Susquehanna County
Other
3.6 MWIn study Susquehanna, PAPJM Oct 2021target 2023
Solar project AH2-024, Jefferson County
Solar
3.0 MWIn study Jefferson, PAPJM Oct 2021target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)