Interconnection queue in Oregon (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3219.1 GW
Active in queue19.1 GW32 requests
Agreement signed2,037 MW8 requests
Withdrawn2115.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

32 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G0695, Crook County
Other
3,600 MWIn study Crook, ORWest Sep 2021target 2028
Solar + storage project G0681, Wasco County
Solar + storage
2,000 MWIn study Wasco, ORWest Jul 2021target 2026
Solar + storage project G0699, Crook County
Solar + storage
1,800 MWIn study Crook, ORWest Sep 2021target 2025
Other project G0675, Crook County
Other
1,800 MWIn study Crook, ORWest Mar 2021target 2029
Solar project G0678, Morrow County
Solar
1,200 MWIn study Morrow, ORWest Jun 2021target 2024
Solar + storage project G0702, Crook County
Solar + storage
1,200 MWIn study Crook, ORWest Sep 2021target 2025
Solar project G0687, Sherman County
Solar
900 MWIn study Sherman, ORWest Aug 2021target 2024
Solar project G0669, Crook County
Solar
600 MWIn study Crook, ORWest Feb 2021target 2027
Battery storage project 622, Malheur County
Battery storage Β· Owyhee Energy Storage, LLC
600 MWAgreement signed Malheur, ORWest Oct 2021target 2029
Solar project G0673, Crook County
Solar
600 MWIn study Crook, ORWest Mar 2021target 2028
Solar project G0712, Sherman County
Solar
448 MWIn study Sherman, ORWest Nov 2021target 2025
Battery storage project 21-104, Washington County
Battery storage
400 MWAgreement signed Washington, ORWest Aug 2021target 2028
Solar + storage project C1-44, Lake County
Solar + storage Β· Archway Solar Energy LLC
400 MWPaused / redesign Lake, ORWest May 2021target 2025
Solar + storage project G0715, Sherman County
Solar + storage
400 MWIn study Sherman, ORWest Dec 2021target 2025
Solar + storage project G0714, Sherman County
Solar + storage
400 MWIn study Sherman, ORWest Dec 2021target 2025
Other project G0693, Crook County
Other
300 MWIn study Crook, ORWest Sep 2021target 2025
Solar project G0711, Sherman County
Solar
300 MWIn study Sherman, ORWest Nov 2021target 2025
Solar + storage project 21-098, Jefferson County
Solar + storage
250 MWAgreement signed Jefferson, ORWest Apr 2021target 2034
Battery storage project 21-103, Clackamas County
Battery storage
200 MWIn study Clackamas, ORWest May 2021target 2033
Solar + storage project G0694, Crook County
Solar + storage
200 MWIn study Crook, ORWest Sep 2021target 2025
Battery storage project 21-102, Multnomah County
Battery storage
200 MWAgreement signed Multnomah, ORWest May 2021target 2030
Battery storage project 21-099, Washington County
Battery storage
200 MWAgreement signed Washington, ORWest May 2021target 2027
Battery storage project 21-100, Washington County
Battery storage
200 MWAgreement signed Washington, ORWest May 2021target 2028
Solar + storage project C1-20, Linn County
Solar + storage Β· Muddy Creek Energy Park LLC
199 MWPaused / redesign Linn, ORWest May 2021target 2025
Solar + storage project C1-46, Klamath County
Solar + storage Β· Diamond Solar Energy LLC
199 MWIn study Klamath, ORWest May 2021target 2029
Battery storage project 21-101, Marion County
Battery storage
185 MWAgreement signed Marion, ORWest May 2021target 2035
Solar project G0706, Morrow County
Solar
100 MWIn study Morrow, ORWest Oct 2021target 2024
Solar project G0713, Morrow County
Solar
100 MWIn study Morrow, ORWest Nov 2021target 2026
Battery storage project G0708, Morrow County
Battery storage
60.0 MWIn study Morrow, ORWest Oct 2021target 2023
Battery storage project G0707, Morrow County
Battery storage
60.0 MWIn study Morrow, ORWest Oct 2021target 2023
Battery storage project G0709, Gilliam County
Battery storage
41.0 MWIn study Gilliam, ORWest Oct 2021target 2023
Battery storage project C1-15, Klamath County
Battery storage Β· PacifiCorp
2.3 MWAgreement signed Klamath, ORWest May 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)