United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Oregon (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31,138 MW
Active in queue1,138 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn515,433 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 10-037, Gilliam County
Onshore wind
500 MWPaused / redesign Gilliam, ORWest Aug 2010target 2015
Onshore wind project 10-036, Sherman County
Onshore wind
400 MWPaused / redesign Sherman, ORWest Mar 2010target 2014
Onshore wind project G0435, Morrow County
Onshore wind
238 MWIn study Morrow, ORWest Aug 2010target 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)