United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown142,410 MW
Active in queue341 MW2 requests
Agreement signed341 MW2 requests
Withdrawn142,410 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2011-028, Ellis County
Onshore wind
301 MWWithdrawn / abandoned Ellis, OKSPP Mar 2011target 2014
Onshore wind project GEN-2011-015, Dewey County
Onshore wind
301 MWWithdrawn / abandoned Dewey, OKSPP Mar 2011target 2013
Onshore wind project GEN-2011-024, Dewey County
Onshore wind
299 MWWithdrawn / abandoned Dewey, OKSPP Mar 2011target 2012
Onshore wind project GEN-2011-049, Beckham County
Onshore wind
251 MWWithdrawn / abandoned Beckham, OKSPP Sep 20112020
Onshore wind project GEN-2011-007, Canadian County
Onshore wind
250 MWWithdrawn / abandoned Canadian, OKSPP Mar 2011target 2011
Onshore wind project GEN-2011-029, Grady County
Onshore wind
200 MWWithdrawn / abandoned Grady, OKSPP Mar 2011target 2013
Onshore wind project GEN-2011-006, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSPP Mar 2011target 2013
Onshore wind project GEN-2011-009, Washita County
Onshore wind
150 MWWithdrawn / abandoned Washita, OKSPP Mar 2011target 2013
Onshore wind project GEN-2011-051, Dewey County
Onshore wind
104 MWWithdrawn / abandoned Dewey, OKSPP Sep 20112017
Onshore wind project GEN-2011-013, Murray County
Onshore wind
102 MWWithdrawn / abandoned Murray, OKSPP Mar 2011target 2012
Onshore wind project GEN-2008-105, Noble County
Onshore wind
100 MWWithdrawn / abandoned Noble, OKSPP Sep 2011target 2011
Onshore wind project GEN-2011-060, Dewey County
Onshore wind
80.0 MWWithdrawn / abandoned Dewey, OKSPP Dec 2011target 2013
Onshore wind project GEN-2011-061, Dewey County
Onshore wind
52.0 MWWithdrawn / abandoned Dewey, OKSPP Dec 2011target 2013
Onshore wind project GEN-2011-035, Cotton County
Onshore wind
20.0 MWWithdrawn / abandoned Cotton, OKSPP Jun 2011target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)