United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Ohio (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6723 MW
Active in queue1,127 MW11 requests
Agreement signed723 MW6 requests
Withdrawn525,731 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Firelands Wind
Onshore wind
298 MWAgreement signed Erie, OHPJM Mar 2017target 2027
Kingwood Solar
Solar
175 MWAgreement signed Greene, OHPJM Sep 2017target 2026
Marion County Solar Project
Solar
100 MWAgreement signed Marion, OHPJM Apr 2017target 2025
Angelina Solar I
Solar
80.0 MWAgreement signed Preble, OHPJM Mar 2017target 2027
Eaton OH Solar
Solar
49.9 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Eaton OH Solar
Solar
20.0 MWAgreement signed Preble, OHPJM Feb 2017target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)