Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown182,983 MW
Active in queue200 MW2 requests
Agreement signed200 MW2 requests
Withdrawn182,983 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J628, Grand Forks County
Onshore wind
400 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2017target 2022
Onshore wind project GEN-2017-048, Williams County
Onshore wind
300 MWWithdrawn / abandoned Williams, NDSPP May 2017target 2027
Onshore wind project J713, Oliver County
Onshore wind
300 MWWithdrawn / abandoned Oliver, NDMISO Jun 2017target 2020
Onshore wind project J580, Burleigh County
Onshore wind
298 MWWithdrawn / abandoned Burleigh, NDMISO Jun 2017target 2021
Onshore wind project GEN-2017-056, Morton County
Onshore wind
210 MWWithdrawn / abandoned Morton, NDSPP May 2017target 2020
Solar project J946, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2017target 2020
Onshore wind project J743, Cass County
Onshore wind
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2017target 2020
Onshore wind project J897, Grand Forks County
Onshore wind
190 MWWithdrawn / abandoned Grand Forks, NDMISO Jun 2017target 2024
Onshore wind project J880, Ward County
Onshore wind
150 MWWithdrawn / abandoned Ward, NDMISO Jun 2017target 2020
Onshore wind project J889, Nelson County
Onshore wind
150 MWWithdrawn / abandoned Nelson, NDMISO Jun 2017target 2020
Onshore wind project J705, Morton County
Onshore wind
100 MWWithdrawn / abandoned Morton, NDMISO Jun 2017target 2021
Onshore wind project GEN-2017-216, Ward County
Onshore wind
100 MWWithdrawn / abandoned Ward, NDSPP Nov 2017target 2026
Onshore wind project J940, Burleigh County
Onshore wind
100 MWWithdrawn / abandoned Burleigh, NDMISO Jun 2017target 2019
Onshore wind project J706, Morton County
Onshore wind
100 MWWithdrawn / abandoned Morton, NDMISO Jun 2017target 2021
Solar project J816, Cass County
Solar
60.0 MWWithdrawn / abandoned Cass, NDMISO Jun 2017target 2022
Onshore wind project GEN-2017-235, Ward County
Onshore wind
50.0 MWWithdrawn / abandoned Ward, NDSPP Nov 2017target 2026
Onshore wind project GEN-2017-236, Ward County
Onshore wind
50.0 MWWithdrawn / abandoned Ward, NDSPP Nov 2017target 2026
Solar project J929, Mcintosh County
Solar
25.0 MWWithdrawn / abandoned Mcintosh, NDMISO Jun 2017target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)