Withdrawn queue requests in North Dakota (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5872 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn5872 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-1305, Williams County
Onshore wind
250 MWWithdrawn / abandoned Williams, NDWest May 2013target 2014
Onshore wind project GI-1311, Billings County
Onshore wind
201 MWWithdrawn / abandoned Billings, NDWest Nov 2013target 2017
Onshore wind project GI-1312, Stark County
Onshore wind
201 MWWithdrawn / abandoned Stark, NDWest Nov 2013target 2017
Onshore wind project GI-1308, Ward County
Onshore wind
120 MWWithdrawn / abandoned Ward, NDWest Jul 2013target 2015
Gas project GI-1304, Mckenzie County
Gas
100 MWWithdrawn / abandoned Mckenzie, NDWest Apr 2013target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)