United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in North Dakota (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,487 MW
Active in queue0.8 MW1 requests
Agreement signed0.8 MW1 requests
Withdrawn101,487 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J212, Ward County
Onshore wind
600 MWWithdrawn / abandoned Ward, NDMISO Apr 2011target 2012
Onshore wind project J209, Mcintosh County
Onshore wind
250 MWWithdrawn / abandoned Mcintosh, NDMISO Mar 2011target 2014
Onshore wind project G757, Adams County
Onshore wind
200 MWWithdrawn / abandoned Adams, NDMISO May 2011target 2009
Onshore wind project J218, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, NDMISO Jun 2011target 2012
Onshore wind project G951, Sheridan County
Onshore wind
99.0 MWWithdrawn / abandoned Sheridan, NDMISO Apr 2011target 2010
Onshore wind project G916, Sheridan County
Onshore wind
53.0 MWWithdrawn / abandoned Sheridan, NDMISO Apr 2011target 2010
Onshore wind project MPC02500, Cass County
Onshore wind
50.0 MWWithdrawn / abandoned Cass, NDMISO Apr 2011target 2012
Onshore wind project G696, Cass County
Onshore wind
50.0 MWWithdrawn / abandoned Cass, NDMISO Apr 2011target 2008
Onshore wind project H022, Barnes County
Onshore wind
33.0 MWWithdrawn / abandoned Barnes, NDMISO Apr 2011target 2012
Gas project GI-1107, Divide County
Gas
2.0 MWWithdrawn / abandoned Divide, NDWest Nov 2011target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)