πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in North Carolina (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7737 MW
Active in queue737 MW7 requests
Agreement signed564 MW4 requests
Withdrawn214,415 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Macadamia Solar
Solar
300 MWAgreement signed Washington, NCPJM Sep 2017target 2028
Macadamia Solar
Solar
109 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Sumac Solar
Solar
80.0 MWAgreement signed Bertie, NCPJM Jun 2017target 2028
Solar project 948720, Nash County
Solar Β· Duke Energy Progress, LLC
80.0 MWUnder construction Nash, NCSoutheast Jun 2017target 2025
Macadamia Solar
Solar
75.0 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Sweetleaf Solar
Solar
60.0 MWPaused / redesign Halifax, NCPJM Aug 2017target 2027
Sweetleaf Solar
Solar
33.0 MWPaused / redesign Halifax, NCPJM Aug 2017target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)