United States โ€บ Grid โ€บ Interconnection queues โ€บ North Carolina

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in North Carolina (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown543,841 MW
Active in queue2,105 MW26 requests
Agreement signed999 MW12 requests
Withdrawn543,841 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

54 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 899003, Chatham County
Battery storage ยท Masked
350 MWWithdrawn / abandoned Chatham, NCSoutheast Jun 2023
Battery storage project 898881, Gaston County
Battery storage
200 MWWithdrawn / abandoned Gaston, NCSoutheast Jun 2023
Battery storage project 899005, Wake County
Battery storage ยท Masked
200 MWWithdrawn / abandoned Wake, NCSoutheast Jun 2023
Battery storage project 893373, Person County
Battery storage ยท Duke Energy Progress, LLC
150 MWWithdrawn / abandoned Person, NCSoutheast Jun 2023
Solar project 896943, Wayne County
Solar
80.0 MWWithdrawn / abandoned Wayne, NCSoutheast Jun 2023
Solar project 909227, Richmond County
Solar
80.0 MWWithdrawn / abandoned Richmond, NCSoutheast Sep 2023
Solar project 897025, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2023
Solar project 920609, Wayne County
Solar
80.0 MWWithdrawn / abandoned Wayne, NCSoutheast Sep 2023
Solar project 920637, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Sep 2023
Solar project 917425, Pitt County
Solar
80.0 MWWithdrawn / abandoned Pitt, NCSoutheast Sep 2023
Solar project 917353, Jones County
Solar
80.0 MWWithdrawn / abandoned Jones, NCSoutheast Sep 2023
Solar project 911073, Robeson County
Solar
80.0 MWWithdrawn / abandoned Robeson, NCSoutheast Sep 2023
Solar project 910089, Greene County
Solar
80.0 MWWithdrawn / abandoned Greene, NCSoutheast Sep 2023
Solar project 917343, Granville County
Solar
80.0 MWWithdrawn / abandoned Granville, NCSoutheast Sep 2023
Solar project 890857, Bladen County
Solar
80.0 MWWithdrawn / abandoned Bladen, NCSoutheast Jun 2023
Solar project 917429, Jones County
Solar
80.0 MWWithdrawn / abandoned Jones, NCSoutheast Sep 2023
Solar project 896799, Hoke County
Solar
80.0 MWWithdrawn / abandoned Hoke, NCSoutheast Jun 2023
Solar project 917677, Duplin County
Solar
80.0 MWWithdrawn / abandoned Duplin, NCSoutheast Sep 2023
Solar project 920641, Bladen County
Solar
80.0 MWWithdrawn / abandoned Bladen, NCSoutheast Sep 2023
Solar project 897027, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2023
Solar project 917441, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Sep 2023
Solar project 910009, Nash County
Solar
78.3 MWWithdrawn / abandoned Nash, NCSoutheast Sep 2023
Solar project 890907, Montgomery County
Solar
75.0 MWWithdrawn / abandoned Montgomery, NCSoutheast Jun 2023
Solar project 921117, Wilson County
Solar
75.0 MWWithdrawn / abandoned Wilson, NCSoutheast Sep 2023
Solar project 890899, Columbus County
Solar
75.0 MWWithdrawn / abandoned Columbus, NCSoutheast Jun 2023
Solar project 920645, Columbus County
Solar
75.0 MWWithdrawn / abandoned Columbus, NCSoutheast Sep 2023
Solar project 920545, Montgomery County
Solar
75.0 MWWithdrawn / abandoned Montgomery, NCSoutheast Sep 2023
Solar project 918039, Cumberland County
Solar
74.9 MWWithdrawn / abandoned Cumberland, NCSoutheast Sep 2023
Solar project 917625, Lenoir County
Solar
73.9 MWWithdrawn / abandoned Lenoir, NCSoutheast Sep 2023
Solar project 920661, Wayne County
Solar
72.0 MWWithdrawn / abandoned Wayne, NCSoutheast Sep 2023
Solar project 910409, Harnett County
Solar
70.0 MWWithdrawn / abandoned Harnett, NCSoutheast Sep 2023
Solar project 897335, Robeson County
Solar
70.0 MWWithdrawn / abandoned Robeson, NCSoutheast Jun 2023
Solar project 918065, Wilson County
Solar
70.0 MWWithdrawn / abandoned Wilson, NCSoutheast Sep 2023
Solar project 890837, Montgomery County
Solar
70.0 MWWithdrawn / abandoned Montgomery, NCSoutheast Jun 2023
Solar project 910061, Greene County
Solar
65.0 MWWithdrawn / abandoned Greene, NCSoutheast Sep 2023
Solar project 898595, Richmond County
Solar ยท Masked
60.0 MWWithdrawn / abandoned Richmond, NCSoutheast Jun 2023
Solar project 920653, Robeson County
Solar
55.0 MWWithdrawn / abandoned Robeson, NCSoutheast Sep 2023
Solar project 918573, Vance County
Solar ยท Masked
55.0 MWWithdrawn / abandoned Vance, NCSoutheast Sep 2023
Solar project 915755, Bladen County
Solar
50.0 MWWithdrawn / abandoned Bladen, NCSoutheast Sep 2023
Battery storage project 900495, Durham County
Battery storage
49.9 MWWithdrawn / abandoned Durham, NCSoutheast Jun 2023
Solar project 920715, Duplin County
Solar
49.9 MWWithdrawn / abandoned Duplin, NCSoutheast Sep 2023
Solar project 916613, Richmond County
Solar
46.5 MWWithdrawn / abandoned Richmond, NCSoutheast Sep 2023
Solar project 610944, Richmond County
Solar
46.5 MWWithdrawn / abandoned Richmond, NCSoutheast Apr 2023
Solar project 918003, Hoke County
Solar
45.0 MWWithdrawn / abandoned Hoke, NCSoutheast Sep 2023
Solar project 920657, Davidson County
Solar
28.8 MWWithdrawn / abandoned Davidson, NCSoutheast Sep 2023
Other project 886387, Columbus County
Other
21.9 MWWithdrawn / abandoned Columbus, NCSoutheast Jun 2023
Battery storage project 892419, Person County
Battery storage ยท Duke Energy Progress, LLC
20.5 MWWithdrawn / abandoned Person, NCSoutheast May 2023
Other project 897221, Wake County
Other
9.0 MWWithdrawn / abandoned Wake, NCSoutheast Jun 2023
Solar project 898147, Buncombe County
Solar
8.8 MWWithdrawn / abandoned Buncombe, NCSoutheast Jun 2023
Other project 897237, Sampson County
Other
7.2 MWWithdrawn / abandoned Sampson, NCSoutheast Jun 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)