United States โบ Grid โบ Interconnection queues โบ North Carolina
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in North Carolina (2022 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 567758, Davidson County Gas |
500 MW | Withdrawn / abandoned |
| Solar + storage project AI1-135, Chowan County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project 569986, Richmond County Solar ยท Masked |
275 MW | Withdrawn / abandoned |
| Solar project 569030, Pender County Solar ยท Masked |
200 MW | Withdrawn / abandoned |
| Solar project 568608, Wake County Solar ยท Duke Energy Progress, LLC |
187 MW | Withdrawn / abandoned |
| Solar project 568672, Davie County Solar |
176 MW | Withdrawn / abandoned |
| Solar project 569290, Jones County Solar ยท Duke Energy Progress, LLC |
172 MW | Withdrawn / abandoned |
| Solar project 565542, Wayne County Solar ยท Masked |
160 MW | Withdrawn / abandoned |
| Solar project 568598, Wake County Solar ยท Duke Energy Progress, LLC |
152 MW | Withdrawn / abandoned |
| Wind + storage project AI1-169, Currituck County Wind + storage |
150 MW | Withdrawn / abandoned |
| Battery storage project 565492, Nash County Battery storage ยท Duke Energy Progress, LLC |
138 MW | Withdrawn / abandoned |
| Solar project 569802, Person County Solar ยท Masked |
120 MW | Withdrawn / abandoned |
| Solar project 569238, Duplin County Solar ยท Masked |
112 MW | Withdrawn / abandoned |
| Solar project 566928, Forsyth County Solar |
100 MW | Withdrawn / abandoned |
| Solar project 569644, Lenoir County Solar ยท Duke Energy Progress, LLC |
91.3 MW | Withdrawn / abandoned |
| Solar project 570306, Franklin County Solar ยท Masked |
80.0 MW | Withdrawn / abandoned |
| Solar project 568978, Duplin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 569984, Craven County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 563066, Wayne County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 569072, Davidson County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 570092, Scotland County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 566356, Onslow County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 569086, Jones County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 569144, Duplin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 566240, Bladen County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 564034, Bladen County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 568988, Scotland County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 570034, Hoke County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 564638, Nash County Solar |
78.3 MW | Withdrawn / abandoned |
| Solar project 569168, Montgomery County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 569246, Pender County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 567240, Montgomery County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 569038, Granville County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 569188, Columbus County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project AI1-113, Halifax County Solar + storage |
74.9 MW | Withdrawn / abandoned |
| Solar project 568222, Cumberland County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 569236, Lenoir County Solar |
73.9 MW | Withdrawn / abandoned |
| Solar project 570150, Robeson County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project 568778, Richmond County Solar |
65.0 MW | Withdrawn / abandoned |
| Solar project 566856, Columbus County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project 569234, Johnston County Solar |
51.7 MW | Withdrawn / abandoned |
| Solar project 565970, Wilkes County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project 570148, Caldwell County Battery storage |
5.0 MW | Withdrawn / abandoned |
| Battery storage project 562852, Surry County Battery storage |
2.7 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)