πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in North Carolina (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown372,960 MW
Active in queue150 MW1 requests
Agreement signed150 MW1 requests
Withdrawn372,960 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

37 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AE1-133, Alamance County
Solar
300 MWWithdrawn / abandoned Alamance, NCPJM Sep 2018target 2022
Solar project AE1-236, Edgecombe County
Solar
290 MWWithdrawn / abandoned Edgecombe, NCPJM Sep 2018target 2022
Solar project 22333, Onslow County
Solar Β· Masked
185 MWWithdrawn / abandoned Onslow, NCSoutheast May 2018
Solar project AD2-181, Currituck County
Solar
150 MWWithdrawn / abandoned Currituck, NCPJM Mar 2018target 2018
Solar project AD2-123, Person County
Solar
94.0 MWWithdrawn / abandoned Person, NCPJM Mar 2018target 2021
Solar project 20318, Onslow County
Solar
80.0 MWWithdrawn / abandoned Onslow, NCSoutheast Oct 2018
Solar + storage project AE1-026, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM May 2018target 2022
Solar + storage project AD2-184, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM Mar 2018target 2020
Solar project 20841, Craven County
Solar Β· Masked
80.0 MWWithdrawn / abandoned Craven, NCSoutheast Apr 2018
Solar + storage project AE1-024, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM May 2018target 2021
Solar + storage project AD2-183, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM Mar 2018target 2020
Solar project 20843, Craven County
Solar Β· Masked
80.0 MWWithdrawn / abandoned Craven, NCSoutheast Apr 2018
Solar + storage project AD2-185, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM Mar 2018target 2021
Solar project 21923, Carteret County
Solar Β· Masked
80.0 MWWithdrawn / abandoned Carteret, NCSoutheast May 2018
Solar + storage project AE1-025, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM May 2018target 2021
Solar project 20479, Hoke County
Solar Β· Masked
80.0 MWWithdrawn / abandoned Hoke, NCSoutheast Mar 2018
Solar project 23707, Person County
Solar Β· Masked
80.0 MWWithdrawn / abandoned Person, NCSoutheast Jul 2018
Solar project AD2-195, Washington County
Solar
80.0 MWWithdrawn / abandoned Washington, NCPJM Mar 2018target 2021
Solar project 21933, Jones County
Solar Β· Masked
80.0 MWWithdrawn / abandoned Jones, NCSoutheast May 2018
Solar project 22128, Lenoir County
Solar
79.8 MWWithdrawn / abandoned Lenoir, NCSoutheast Oct 2018
Solar project 22134, Lenoir County
Solar
79.8 MWWithdrawn / abandoned Lenoir, NCSoutheast Aug 2018
Solar project 20853, Beaufort County
Solar Β· Masked
75.0 MWWithdrawn / abandoned Beaufort, NCSoutheast Apr 2018
Solar project AD2-089, Edgecombe County
Solar
75.0 MWWithdrawn / abandoned Edgecombe, NCPJM Mar 2018target 2020
Solar project 20857, Beaufort County
Solar Β· Masked
75.0 MWWithdrawn / abandoned Beaufort, NCSoutheast Apr 2018
Solar project AD2-051, Hertford County
Solar
74.9 MWWithdrawn / abandoned Hertford, NCPJM Jan 2018target 2020
Solar project AE1-019, Hertford County
Solar
70.0 MWWithdrawn / abandoned Hertford, NCPJM May 2018target 2021
Solar project 65312, Rowan County
Solar
69.0 MWWithdrawn / abandoned Rowan, NCSoutheast Jun 2018
Solar project 26829, Johnston County
Solar Β· Masked
50.0 MWWithdrawn / abandoned Johnston, NCSoutheast Dec 2018
Solar project AD2-068, Pitt County
Solar
50.0 MWWithdrawn / abandoned Pitt, NCPJM Feb 2018target 2020
Solar project 23715, Person County
Solar Β· Masked
20.0 MWWithdrawn / abandoned Person, NCSoutheast Jul 2018
Battery storage project AE1-005, Beaufort County
Battery storage
20.0 MWWithdrawn / abandoned Beaufort, NCPJM Apr 2018target 2020
Battery storage project AE1-088, Beaufort County
Battery storage
20.0 MWWithdrawn / abandoned Beaufort, NCPJM Aug 2018target 2020
Solar project AD2-124, Person County
Solar
20.0 MWWithdrawn / abandoned Person, NCPJM Mar 2018target 2021
Battery storage project AD2-094, Beaufort County
Battery storage
20.0 MWWithdrawn / abandoned Beaufort, NCPJM Mar 2018target 2020
Solar project 21764, Lenoir County
Solar
8.0 MWWithdrawn / abandoned Lenoir, NCSoutheast Oct 2018
Solar project 21772, Lenoir County
Solar
8.0 MWWithdrawn / abandoned Lenoir, NCSoutheast Oct 2018
Solar project 19261, Scotland County
Solar
6.2 MWWithdrawn / abandoned Scotland, NCSoutheast Jan 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)