Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AE1-133, Alamance County Solar |
300 MW | Withdrawn / abandoned |
| Solar project AE1-236, Edgecombe County Solar |
290 MW | Withdrawn / abandoned |
| Solar project 22333, Onslow County Solar Β· Masked |
185 MW | Withdrawn / abandoned |
| Solar project AD2-181, Currituck County Solar |
150 MW | Withdrawn / abandoned |
| Solar project AD2-123, Person County Solar |
94.0 MW | Withdrawn / abandoned |
| Solar project 20318, Onslow County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-026, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AD2-184, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 20841, Craven County Solar Β· Masked |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-024, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AD2-183, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 20843, Craven County Solar Β· Masked |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AD2-185, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 21923, Carteret County Solar Β· Masked |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-025, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 20479, Hoke County Solar Β· Masked |
80.0 MW | Withdrawn / abandoned |
| Solar project 23707, Person County Solar Β· Masked |
80.0 MW | Withdrawn / abandoned |
| Solar project AD2-195, Washington County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 21933, Jones County Solar Β· Masked |
80.0 MW | Withdrawn / abandoned |
| Solar project 22128, Lenoir County Solar |
79.8 MW | Withdrawn / abandoned |
| Solar project 22134, Lenoir County Solar |
79.8 MW | Withdrawn / abandoned |
| Solar project 20853, Beaufort County Solar Β· Masked |
75.0 MW | Withdrawn / abandoned |
| Solar project AD2-089, Edgecombe County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 20857, Beaufort County Solar Β· Masked |
75.0 MW | Withdrawn / abandoned |
| Solar project AD2-051, Hertford County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project AE1-019, Hertford County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project 65312, Rowan County Solar |
69.0 MW | Withdrawn / abandoned |
| Solar project 26829, Johnston County Solar Β· Masked |
50.0 MW | Withdrawn / abandoned |
| Solar project AD2-068, Pitt County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project 23715, Person County Solar Β· Masked |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-005, Beaufort County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-088, Beaufort County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AD2-124, Person County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AD2-094, Beaufort County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project 21764, Lenoir County Solar |
8.0 MW | Withdrawn / abandoned |
| Solar project 21772, Lenoir County Solar |
8.0 MW | Withdrawn / abandoned |
| Solar project 19261, Scotland County Solar |
6.2 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)