United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in New Mexico (2020 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project GEN-2020-065, Gaines County Gas |
1,003 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-04, Bernalillo County Solar + storage |
400 MW | Agreement signed |
| Atrisco Solar II Solar + storage |
300 MW | Paused / redesign |
| Battery storage project IA-PNM-2020-17, Bernalillo County Battery storage Β· AES Renewable Holdings |
150 MW | Agreement signed |
| Onshore wind project IA-PNM-2020-01, Guadalupe County Onshore wind |
145 MW | Agreement signed |
| Zinnia Storage Battery storage |
100 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-07, San Juan County Solar + storage |
100 MW | In study |
| Solar + storage project IA-PNM-2020-21, Valencia County Solar + storage |
100 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-06, Mckinley County Solar + storage |
90.0 MW | In study |
| Ambrosia Solar Solar + storage Β· Ambrosia Solar |
90.0 MW | Paused / redesign |
| Wildcat Solar Power Plant Solar + storage |
90.0 MW | Paused / redesign |
| Gas project IA-PNM-2020-05, San Juan County Gas Β· PNM βΓΓ¬ Generation |
80.0 MW | Agreement signed |
| Iris Del Sol Solar + storage |
76.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)