United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Mexico (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown141,743 MW
Active in queue1,743 MW14 requests
Agreement signed1,518 MW12 requests
Withdrawn283,557 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IA-PNM-2017-13, San Juan County
Solar + storage
500 MWAgreement signed San Juan, NMWest Oct 2017target 2020
EC500W Project
Onshore wind
247 MWAgreement signed Chaves, NMWest Jul 2017target 2020
Gas project IA-PNM-2017-14, San Juan County
Gas
236 MWAgreement signed San Juan, NMWest Oct 2017target 2022
D150S Project
Solar + storage
150 MWPaused / redesign Dona Ana, NMWest Sep 2017target 2020
NMRD Data Center IV
Solar
140 MWAgreement signed Sandoval, NMWest Jan 2017target 2022
AC120SB Project
Solar + storage
120 MWAgreement signed Otero, NMWest Sep 2017target 2022
Solar project IA-PNM-2017-15, San Juan County
Solar
95.6 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Solar + storage project IA-PNM-2017-11, Torrance County
Solar + storage
74.9 MWIn study Torrance, NMWest Jun 2017target 2020
Solar project IA-PNM-2017-07, Sandoval County
Solar Β· NM Renewable Development
50.0 MWAgreement signed Sandoval, NMWest Jan 2017target 2022
NMRD Data Center IV
Solar
50.0 MWAgreement signed Santa Fe, NMWest Jan 2017target 2022
Solar project IA-PNM-2017-06, Sandoval County
Solar Β· NM Renewable Development
50.0 MWAgreement signed Sandoval, NMWest Jan 2017target 2022
Solar project SGI-PNM-2017-08, Luna County
Solar
11.0 MWAgreement signed Luna, NMWest Jun 2017target 2019
Solar project IA-PNM-2017-01, Cibola County
Solar Β· NextEra Energy
10.0 MWAgreement signed Cibola, NMWest Jan 2017target 2021
Solar project SGI-PNM-2017-09, Luna County
Solar
8.3 MWAgreement signed Luna, NMWest Jun 2017target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)