United States βΊ Grid βΊ Interconnection queues βΊ New Jersey
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in New Jersey (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Larrabee 230 kV IV Offshore wind Β· Atlantic Shores Offshore Wind Project 2, LLC |
1,300 MW | Withdrawn / abandoned |
| Offshore wind project AH1-506, Monmouth County Offshore wind |
730 MW | Withdrawn / abandoned |
| Offshore wind project AH1-507, Monmouth County Offshore wind |
730 MW | Withdrawn / abandoned |
| Offshore wind project AH1-556, Monmouth County Offshore wind |
360 MW | Withdrawn / abandoned |
| Brunswick Energy Storage Battery storage Β· East Coast Power LLC |
165 MW | Withdrawn / abandoned |
| Battery storage project AH1-043, Middlesex County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-224, Essex County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Solar project AG2-241, Cumberland County Solar |
47.0 MW | Withdrawn / abandoned |
| Hydro project AG2-172, Warren County Hydro |
30.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-531, Morris County Battery storage Β· West Denville LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-588, Warren County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-537, Hunterdon County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-204, Essex County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-536, Hunterdon County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-530, Salem County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-189, Warren County Solar Β· Harmony Sand Solar Farm, LLC |
19.8 MW | Withdrawn / abandoned |
| Solar project AG2-600, Warren County Solar Β· East Asbury Anderson Solar Farm, LLC |
19.6 MW | Withdrawn / abandoned |
| Solar project AG2-624, Warren County Solar |
19.6 MW | Withdrawn / abandoned |
| Solar project AG2-599, Warren County Solar Β· Oxford Textile Solar Farm, LLC |
19.6 MW | Withdrawn / abandoned |
| Solar project AH1-335, Warren County Solar |
19.3 MW | Withdrawn / abandoned |
| Changewater Solar Farm Solar Β· Changewater Solar Farm LLC |
19.3 MW | Withdrawn / abandoned |
| Solar project AH1-068, Gloucester County Solar |
12.0 MW | Withdrawn / abandoned |
| Solar project AG2-228, Warren County Solar Β· Reeder Farm Solar Farm, LLC |
11.2 MW | Withdrawn / abandoned |
| Solar project AH1-067, Gloucester County Solar |
8.5 MW | Withdrawn / abandoned |
| Solar project AG2-257, Ocean County Solar |
8.0 MW | Withdrawn / abandoned |
| Solar project AG2-177, Sussex County Solar |
8.0 MW | Withdrawn / abandoned |
| Solar project AG2-256, Somerset County Solar |
8.0 MW | Withdrawn / abandoned |
| Solar project AH1-411, Warren County Solar |
5.8 MW | Withdrawn / abandoned |
| Solar project AG2-255, Burlington County Solar |
4.0 MW | Withdrawn / abandoned |
| Solar project AG2-254, Burlington County Solar |
4.0 MW | Withdrawn / abandoned |
| Solar project AH1-006, Essex County Solar |
3.7 MW | Withdrawn / abandoned |
| Solar project AH1-077, Burlington County Solar |
3.0 MW | Withdrawn / abandoned |
| Solar project AG2-087, Camden County Solar |
2.5 MW | Withdrawn / abandoned |
| Solar project AH1-638, Atlantic County Solar |
1.6 MW | Withdrawn / abandoned |
| Solar project AG2-144, Salem County Solar |
1.5 MW | Withdrawn / abandoned |
| Burlington Energy Storage Solar + storage |
1.2 MW | Withdrawn / abandoned |
| Solar project AG2-421, Cumberland County Solar |
1.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)