United States โบ Grid โบ Interconnection queues โบ New Jersey
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in New Jersey (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Offshore wind project AE2-251, Monmouth County Offshore wind |
1,200 MW | Withdrawn / abandoned |
| Onshore wind project AF1-101, Ocean County Onshore wind |
800 MW | Withdrawn / abandoned |
| Offshore wind project AF1-222, Monmouth County Offshore wind |
510 MW | Withdrawn / abandoned |
| Onshore wind project AE2-232, Atlantic County Onshore wind |
400 MW | Withdrawn / abandoned |
| Offshore wind project AE2-222, Atlantic County Offshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project AF1-126, Burlington County Battery storage |
250 MW | Withdrawn / abandoned |
| Battery storage project AF2-016, Atlantic County Battery storage ยท Garden Reserve Energy, LLC |
240 MW | Withdrawn / abandoned |
| Solar project AF1-081, Atlantic County Solar |
160 MW | Withdrawn / abandoned |
| Solar + storage project AF1-052, Hudson County Solar + storage |
132 MW | Withdrawn / abandoned |
| Battery storage project AE2-237, Sussex County Battery storage |
107 MW | Withdrawn / abandoned |
| Battery storage project AF1-303, Atlantic County Battery storage |
107 MW | Withdrawn / abandoned |
| Brunswick Energy Storage Battery storage ยท JERA Americas Inc. |
100 MW | Withdrawn / abandoned |
| Solar project AE2-317, Atlantic County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project AE2-205, Cumberland County Solar |
78.0 MW | Withdrawn / abandoned |
| Solar project AE2-314, Atlantic County Solar |
72.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-107, Warren County Battery storage |
60.0 MW | Withdrawn / abandoned |
| Solar project AE2-335, Gloucester County Solar |
60.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-022, Cumberland County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Horse Run Solar I Solar + storage |
45.0 MW | Withdrawn / abandoned |
| Gloucester Solar I Solar |
44.0 MW | Withdrawn / abandoned |
| Solar project AE2-039, Gloucester County Solar |
44.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-023, Salem County Battery storage |
42.5 MW | Withdrawn / abandoned |
| Solar project AE2-091, Cumberland County Solar |
35.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-026, Cumberland County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Mickleton Battery Storage Battery storage |
24.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-160, Camden County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Mansfield #2 Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AF1-109, Mercer County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Holly Glen Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AF1-145, Morris County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AF1-008, Morris County Solar |
20.0 MW | Withdrawn / abandoned |
| Denville Storage Facility Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AF1-108, Hunterdon County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Carll's Corner Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Mansfield #1 Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-021, Ocean County Battery storage ยท Calpine Mid-Atlantic Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AE2-082, Monmouth County Solar |
7.0 MW | Withdrawn / abandoned |
| Solar + storage project AE2-085, Burlington County Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AE2-102, Burlington County Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Solar project AE2-200, Salem County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AE2-201, Hunterdon County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AE2-197, Hunterdon County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AE2-068, Cumberland County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AE2-069, Burlington County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar + storage project AE2-106, Cumberland County Solar + storage |
4.9 MW | Withdrawn / abandoned |
| Solar project AE2-066, Gloucester County Solar |
4.5 MW | Withdrawn / abandoned |
| Solar + storage project AE2-087, Cumberland County Solar + storage |
4.5 MW | Withdrawn / abandoned |
| Solar project AE2-203, Warren County Solar |
4.4 MW | Withdrawn / abandoned |
| Solar project AE2-075, Cumberland County Solar |
4.4 MW | Withdrawn / abandoned |
| Solar project AE2-101, Gloucester County Solar |
4.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)