πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

SOLAR Β· PJM

Solar project AE2-197, Hunterdon County

Solar project AE2-197, Hunterdon County is a 5.0 MW solar request withdrawn in the PJM interconnection queue, in Hunterdon County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE2-197
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Location
Hunterdon County, New Jersey
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
19 March 2019
Proposed online date
October 2020
Withdrawn
April 2019

Location

Marker shows the centre of Hunterdon County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Hunterdon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem