United States โบ Grid โบ Interconnection queues โบ New Jersey
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in New Jersey (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project AB2-055, Hudson County Gas |
1,041 MW | Withdrawn / abandoned |
| Gas project AB2-082, Middlesex County Gas |
675 MW | Withdrawn / abandoned |
| Cumberland Gas |
230 MW | Withdrawn / abandoned |
| Gas project AB2-091, Hudson County Gas |
105 MW | Withdrawn / abandoned |
| Gateway Energy Center Gas |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AB2-094, Hunterdon County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AC1-104, Salem County Solar |
19.8 MW | Withdrawn / abandoned |
| Battery storage project AB2-127, Hunterdon County Battery storage |
16.0 MW | Withdrawn / abandoned |
| Solar project AC1-020, Sussex County Solar |
12.2 MW | Withdrawn / abandoned |
| Solar project AB2-111, Monmouth County Solar |
11.1 MW | Withdrawn / abandoned |
| Solar project AB2-110, Monmouth County Solar |
11.1 MW | Withdrawn / abandoned |
| Solar project AC1-205, Middlesex County Solar |
10.3 MW | Withdrawn / abandoned |
| Solar project AB2-044, Middlesex County Solar |
10.0 MW | Withdrawn / abandoned |
| Burlington 26 kV Solar Solar |
8.8 MW | Withdrawn / abandoned |
| Solar project AB2-121, Burlington County Solar |
5.0 MW | Withdrawn / abandoned |
| Gas project AC1-066, Union County Gas |
5.0 MW | Withdrawn / abandoned |
| Solar project AC1-090, Atlantic County Solar |
4.0 MW | Withdrawn / abandoned |
| Solar project AC1-014, Monmouth County Solar |
4.0 MW | Withdrawn / abandoned |
| Meadow Road Solar Solar |
2.5 MW | Withdrawn / abandoned |
| Winzinger Egg Harbor Solar Project Solar |
1.9 MW | Withdrawn / abandoned |
| Solar project AC1-084, Morris County Solar |
1.6 MW | Withdrawn / abandoned |
| Battery storage project AC1-119, Middlesex County Battery storage |
1.5 MW | Withdrawn / abandoned |
| Solar project AB2-119, Cape May County Solar |
1.5 MW | Withdrawn / abandoned |
| Strykers Road Solar Farm Solar |
1.4 MW | Withdrawn / abandoned |
| Battery storage project AC1-026, Atlantic County Battery storage |
1.3 MW | Withdrawn / abandoned |
| Solar project AB2-159, Burlington County Solar |
1.3 MW | Withdrawn / abandoned |
| Battery storage project AC1-170, Mercer County Battery storage |
1.0 MW | Withdrawn / abandoned |
| Battery storage project AB2-017, Atlantic County Battery storage |
1.0 MW | Withdrawn / abandoned |
| Lake Nelson 13 kV Solar Solar |
0.9 MW | Withdrawn / abandoned |
| Hillside Battery Battery storage |
0.5 MW | Withdrawn / abandoned |
| Clinton Energy Storage System Battery storage |
0.5 MW | Withdrawn / abandoned |
| Battery storage project AC1-077, Middlesex County Battery storage |
0.4 MW | Withdrawn / abandoned |
| Solar project AC1-015, Monmouth County Solar |
0.4 MW | Withdrawn / abandoned |
| Battery storage project AC1-218, Morris County Battery storage |
0.3 MW | Withdrawn / abandoned |
| Camden 480v III Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AB2-163, Camden County Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AB2-162, Camden County Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AB2-107, Burlington County Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AB2-106, Middlesex County Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AB2-108, Atlantic County Gas |
0.2 MW | Withdrawn / abandoned |
| Mercer 480v II Gas |
0.2 MW | Withdrawn / abandoned |
| The Home Depot Store #0951 Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AC1-196, Gloucester County Gas |
0.2 MW | Withdrawn / abandoned |
| Somerset 480v Gas |
0.2 MW | Withdrawn / abandoned |
| Battery storage project AC1-219, Morris County Battery storage |
0.2 MW | Withdrawn / abandoned |
| Camden 480v II Gas |
0.2 MW | Withdrawn / abandoned |
| Mercer 480v I Gas |
0.2 MW | Withdrawn / abandoned |
| Union 480v Gas |
0.2 MW | Withdrawn / abandoned |
| Gas project AB2-105, Gloucester County Gas |
0.2 MW | Withdrawn / abandoned |
| Battery storage project AB2-066, Monmouth County Battery storage |
0.1 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)