Solar project AC1-205, Middlesex County

Solar project AC1-205, Middlesex County is a 10.3 MW solar request withdrawn in the PJM interconnection queue, in Middlesex County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandonedNov 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC1-205
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Madison Park
Location
Middlesex County, New Jersey
Technology
Solar: 10.3 MW
Total requested
10.3 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 October 2016
Proposed online date
December 2017
Withdrawn
November 2016

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Middlesex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem