United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in New Jersey (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15377 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn121,566 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Linden Generating Station
Gas
61.0 MWOperating Union, NJPJM Nov 20132018
Gas project Y3-052, Bergen County
Gas
50.0 MWOperating Bergen, NJPJM Feb 20132015
Linden Generating Station
Gas
47.0 MWOperating Union, NJPJM Feb 20132016
Gas project Y3-107, Bergen County
Gas
45.0 MWOperating Bergen, NJPJM Apr 20132015
Kearny Generating Station
Gas
40.0 MWOperating Hudson, NJPJM Feb 20132015
Linden Generating Station
Gas
36.0 MWOperating Union, NJPJM Sep 20132016
Kearny Generating Station
Gas
24.0 MWOperating Hudson, NJPJM Feb 20132015
Linden Generating Station
Gas
23.0 MWOperating Union, NJPJM Sep 20132016
Yards Creek Pumped Storage Hydro-electric Generating Station
Hydro
20.0 MWOperating Warren, NJPJM Aug 20132014
Burlington (L&D Solar) 26kV
Solar
10.0 MWOperating Burlington, NJPJM Jan 20132016
Parkland Solar
Solar
7.8 MWOperating Burlington, NJPJM Oct 20132015
Kearny Generating Station
Gas
5.0 MWOperating Hudson, NJPJM Feb 20132015
Beaverbrook (Kinsley Solar)
Solar
3.8 MWOperating Gloucester, NJPJM Apr 20132015
Burlington Generating Station
Gas
3.0 MWOperating Burlington, NJPJM Feb 20132015
Lawnside Battery
Battery storage
1.0 MWOperating Camden, NJPJM Oct 20132015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)