πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in Nevada

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3690 MW
Active in queue690 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn113,929 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Company NA, White Pine County
Onshore wind
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Onshore wind project NVE
Onshore wind
200 MWIn study NVWest target 2014
Onshore wind project Company NO, Storey County
Onshore wind
190 MWPaused / redesign Storey, NVWest Mar 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)