United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nevada (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown111,145 MW
Active in queue1,522 MW10 requests
Agreement signed533 MW7 requests
Withdrawn111,145 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Company 152, Clark County
Solar
255 MWWithdrawn / abandoned Clark, NVWest Mar 2017target 2020
Solar + storage project Q61, Clark County
Solar + storage
250 MWWithdrawn / abandoned Clark, NVWest Jul 2017target 2020
Solar project Company HY, Lander County
Solar
200 MWWithdrawn / abandoned Lander, NVWest Sep 2017target 2019
Solar + storage project Company HZ, Humboldt County
Solar + storage
120 MWWithdrawn / abandoned Humboldt, NVWest Sep 2017target 2020
Solar project Company HR, Lyon County
Solar
100 MWWithdrawn / abandoned Lyon, NVWest Sep 2017target 2021
Warren Solar 1
Solar
71.5 MWWithdrawn / abandoned Nye, NVCAISO May 2017target 2020
Geothermal project Company HO, Pershing County
Geothermal
45.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2017target 2026
Geothermal project Company HW, Esmerelda County
Geothermal
38.5 MWWithdrawn / abandoned Esmerelda, NVWest Sep 2017target 2020
Geothermal project Company HV, Washoe County
Geothermal
38.5 MWWithdrawn / abandoned Washoe, NVWest Sep 2017target 2024
Solar project Company HX, Washoe County
Solar
25.0 MWWithdrawn / abandoned Washoe, NVWest Sep 2017target 2020
Solar project Company 154, Clark County
Solar
1.5 MWWithdrawn / abandoned Clark, NVWest Jun 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)