Interconnection queue in Nebraska (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown142,939 MW
Active in queue2,939 MW14 requests
Agreement signed0.0 MW0 requests
Withdrawn1150 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-021, Lancaster County
Gas
540 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2024-020, Lancaster County
Gas
390 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2024-022, Gage County
Gas
390 MWIn study Gage, NESPP Oct 2024target 2030
Solar project GEN-2024-038, Nemaha County
Solar
300 MWIn study Nemaha, NESPP Oct 2024target 2029
Gas project GEN-2024-023, Gage County
Gas
270 MWIn study Gage, NESPP Oct 2024target 2030
Solar project GEN-2024-039, Nemaha County
Solar
250 MWIn study Nemaha, NESPP Oct 2024target 2029
Solar project GEN-2024-040, Nemaha County
Solar
174 MWIn study Nemaha, NESPP Oct 2024target 2029
Battery storage project GEN-2024-051, Lancaster County
Battery storage
170 MWIn study Lancaster, NESPP Oct 2024target 2028
Battery storage project GEN-2024-065, Dodge County
Battery storage
150 MWIn study Dodge, NESPP Oct 2024target 2029
Battery storage project GEN-2024-SR10, Lancaster County
Battery storage
80.0 MWIn study Lancaster, NESPP Apr 2024target 2026
Battery storage project GEN-2024-SR8, Greeley County
Battery storage
70.0 MWIn study Greeley, NESPP Apr 2024target 2026
Gas project GEN-2024-019, Gage County
Gas
62.0 MWIn study Gage, NESPP Oct 2024target 2030
Gas project GEN-2024-017, Lancaster County
Gas
62.0 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2024-018, Gage County
Gas
31.0 MWIn study Gage, NESPP Oct 2024target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)