United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Nebraska (2023 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project GEN-2023-222, Gage County Gas |
478 MW | In study |
| Gas project GEN-2023-224, Lancaster County Gas |
478 MW | In study |
| Gas project GEN-2023-079, Cass County Gas |
273 MW | In study |
| Gas project GEN-2023-077, Cass County Gas |
255 MW | In study |
| Gas project GEN-2023-078, Cass County Gas |
255 MW | In study |
| Solar + storage project GEN-2023-199, Dakota County Solar + storage |
250 MW | In study |
| Gas project GEN-2023-223, Gage County Gas |
239 MW | In study |
| Gas project GEN-2023-225, Lancaster County Gas |
217 MW | In study |
| Solar + storage project GEN-2023-153, Perkins County Solar + storage |
120 MW | In study |
| Battery storage project GEN-2023-SR19, Jefferson County Battery storage |
50.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)