OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Nebraska (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GEN-2021-057, Antelope County Onshore wind |
300 MW | In study |
| Battery storage project GEN-2021-043, Lancaster County Battery storage |
250 MW | Agreement signed |
| Solar project GEN-2021-049, Lancaster County Solar |
225 MW | Agreement signed |
| Battery storage project GEN-2021-040, Cass County Battery storage |
200 MW | In study |
| Solar project GEN-2021-108, Cass County Solar |
182 MW | In study |
| Solar project GEN-2021-034, Lancaster County Solar |
113 MW | Agreement signed |
| Solar project GEN-2021-027, Lancaster County Solar |
102 MW | In study |
| Battery storage project GEN-2021-039, Douglas County Battery storage |
100 MW | In study |
| Battery storage project GEN-2021-048, Lancaster County Battery storage |
75.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)