Withdrawn queue requests in Nebraska (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9866 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn9866 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2010-035, Richardson County
Onshore wind
160 MWWithdrawn / abandoned Richardson, NESPP Jun 2010target 2014
Onshore wind project GEN-2010-039, Holt County
Onshore wind
150 MWWithdrawn / abandoned Holt, NESPP Aug 2010target 2012
Onshore wind project GEN-2010-010, Madison County
Onshore wind
101 MWWithdrawn / abandoned Madison, NESPP Mar 2010target 2012
Onshore wind project GEN-2010-024, Cherry County
Onshore wind
100 MWWithdrawn / abandoned Cherry, NESPP Mar 2010target 2011
Onshore wind project GEN-2010-026, Wayne County
Onshore wind
99.0 MWWithdrawn / abandoned Wayne, NESPP Mar 2010target 2012
Onshore wind project GEN-2010-044, Jefferson County
Onshore wind
99.0 MWWithdrawn / abandoned Jefferson, NESPP Sep 2010target 2012
Onshore wind project GEN-2010-038, Custer County
Onshore wind
74.9 MWWithdrawn / abandoned Custer, NESPP Aug 2010target 2012
Onshore wind project GEN-2010-047, Jefferson County
Onshore wind
72.0 MWWithdrawn / abandoned Jefferson, NESPP Sep 2010target 2012
Onshore wind project GEN-2010-041, Richardson County
Onshore wind
10.3 MWWithdrawn / abandoned Richardson, NESPP Sep 20102015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)