OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Montana (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5413 MW
Active in queue413 MW5 requests
Agreement signed0.0 MW0 requests
Withdrawn4359 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 465, Stillwater County
Gas
150 MWIn study Stillwater, MTWest Jun 2024target 2029
Gas project 464, Broadwater County
Gas
150 MWIn study Broadwater, MTWest Jun 2024target 2029
Battery storage project 455, Yellowstone County
Battery storage
100 MWIn study Yellowstone, MTWest Jan 2024target 2028
Hydro project 458, Broadwater County
Hydro
10.4 MWIn study Broadwater, MTWest Apr 2024
Hydro project 457, Lewis And Clark County
Hydro
2.2 MWIn study Lewis And Clark, MTWest Mar 2024target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)