OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Montana (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,914 MW
Active in queue1,914 MW10 requests
Agreement signed0.0 MW0 requests
Withdrawn5286 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 408, Wheatland County
Onshore wind
326 MWIn study Wheatland, MTWest Feb 2021target 2024
Onshore wind project C013, Meagher County
Onshore wind
326 MWIn study Meagher, MTWest Jan 2021target 2024
Onshore wind project 407, Rosebud County
Onshore wind
300 MWIn study Rosebud, MTWest Feb 2021target 2024
Onshore wind project 406, Rosebud County
Onshore wind
300 MWIn study Rosebud, MTWest Feb 2021target 2024
Solar project 405, Rosebud County
Solar
300 MWPaused / redesign Rosebud, MTWest Feb 2021target 2024
Solar + storage project 416, Broadwater County
Solar + storage
160 MWPaused / redesign Broadwater, MTWest Sep 2021target 2023
Solar + storage project 412, Gallatin County
Solar + storage
80.0 MWPaused / redesign Gallatin, MTWest Jun 2021
Onshore wind project 401, Musselshell County
Onshore wind
70.0 MWIn study Musselshell, MTWest Jan 2021target 2023
Solar + storage project 417, Wheatland County
Solar + storage
50.0 MWIn study Wheatland, MTWest Nov 2021target 2022
Other project G0710, Flathead County
Other
1.6 MWIn study Flathead, MTWest Nov 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)