United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Montana (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,594 MW
Active in queue1,594 MW6 requests
Agreement signed74.5 MW1 requests
Withdrawn263,612 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project C012, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jul 2020target 2023
Other project 390, Yellowstone County
Other
500 MWIn study Yellowstone, MTWest Aug 2020target 2023
Gas project 378, Yellowstone County
Gas
175 MWIn study Yellowstone, MTWest May 2020target 2023
Solar + storage project GEN-2020-083, Richland County
Solar + storage
74.5 MWAgreement signed Richland, MTSPP Apr 2020target 2032
Battery storage project 376, Yellowstone County
Battery storage
58.8 MWPaused / redesign Yellowstone, MTWest May 2020target 2023
Gas project 377, Silver Bow County
Gas
36.0 MWPaused / redesign Silver Bow, MTWest May 2020target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)