United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Montana (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,865 MW
Active in queue1,865 MW6 requests
Agreement signed125 MW1 requests
Withdrawn161,147 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 356, Rosebud County
Onshore wind
750 MWIn study Rosebud, MTWest Oct 2018target 2021
Onshore wind project 357, Rosebud County
Onshore wind
750 MWIn study Rosebud, MTWest Oct 2018target 2021
Wind + storage project 347, Wheatland County
Wind + storage
140 MWPaused / redesign Wheatland, MTWest Jul 2018target 2024
Onshore wind project GEN-2018-069, Wibaux County
Onshore wind
125 MWAgreement signed Wibaux, MTSPP Oct 2018target 2031
Solar + storage project 358, Yellowstone County
Solar + storage
80.0 MWPaused / redesign Yellowstone, MTWest Oct 2018target 2022
Solar + storage project 340, Yellowstone County
Solar + storage
20.0 MWIn study Yellowstone, MTWest Mar 2018target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)