Interconnection queue in Missouri (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown93,328 MW
Active in queue3,328 MW9 requests
Agreement signed3,128 MW8 requests
Withdrawn183,119 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-83, Randolph County
Onshore wind
1,018 MWAgreement signed Randolph, MOSoutheast Jun 2019target 2027
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Solar project GEN-2019-016, Polk County
Solar
200 MWAgreement signed Polk, MOSPP Apr 2019target 2029
Solar project J1299, Scott County
Solar
200 MWUnder construction Scott, MOMISO Apr 2019target 2025
Solar project J1268, Lincoln County
Solar
150 MWAgreement signed Lincoln, MOMISO Apr 2019target 2023
Solar project GI-86, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Oct 2019target 2027
Solar project J1352, Montgomery County
Solar
100 MWAgreement signed Montgomery, MOMISO Apr 2019target 2024
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)