United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Missouri

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown198,345 MW
Active in queue8,345 MW19 requests
Agreement signed1,160 MW7 requests
Withdrawn155,223 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3996, St. Charles County
Gas
2,220 MWIn study St. Charles, MOMISO Apr 2025target 2030
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff
Gas
824 MWIn study St. Louis, MOMISO May 2024target 2025
Gas project GEN-2024-207, Jackson County
Gas
779 MWIn study Jackson, MOSPP Mar 2025target 2029
Gas project GI-132, Butler County
Gas
460 MWIn study Butler, MOSoutheast Jul 2025target 2030
Gas project GI-131, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jul 2025target 2030
Gas project GI-126, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jan 2025target 2029
Gas project GI-128, Clinton County
Gas
460 MWIn study Clinton, MOSoutheast Jul 2025target 2030
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Gas project ERAS-2025-007, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Oct 2025target 2030
Gas project ERAS-2025-013, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Sep 2025target 2030
Gas project ERAS-2025-034, Jasper County
Gas
250 MWIn study Jasper, MOSPP Sep 2025target 2030
Gas project GEN-2024-206, Jackson County
Gas
226 MWIn study Jackson, MOSPP Mar 2025target 2026
Gas project GEN-2024-088, Greene County
Gas
145 MWIn study Greene, MOSPP Oct 2024target 2027
Gas project GI-102, Clinton County
Gas
75.0 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Gas project GEN-2020-064, Jasper County
Gas
64.0 MWAgreement signed Jasper, MOSPP Apr 20202025
Gas project GI-117, New Madrid County
Gas
46.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Gas project GEN-2020-061, Cass County
Gas
29.0 MWAgreement signed Cass, MOSPP Apr 2020target 2026
Gas project GI-116, New Madrid County
Gas
26.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)