United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Minnesota

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9309 MW
Active in queue28.4 GW155 requests
Agreement signed309 MW9 requests
Withdrawn48280.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J569, Rock County
Onshore wind
100 MWAgreement signed Rock, MNMISO May 20162022
Solar project J1164, Rock County
Solar
80.0 MWAgreement signed Rock, MNMISO Mar 2018target 2024
Solar project J523, Mower County
Solar
50.0 MWAgreement signed Mower, MNMISO Nov 20152024
Gas project J485, Olmsted County
Gas
46.9 MWAgreement signed Olmsted, MNMISO Oct 20152018
Onshore wind project G621, Pipestone County
Onshore wind
20.0 MWAgreement signed Pipestone, MNMISO Apr 20062022
Other project G177, Lyon County
Other
5.0 MWAgreement signed Lyon, MNMISO Mar 2002target 2004
Wind + storage project R101, Red Lake County
Wind + storage
4.6 MWAgreement signed Red Lake, MNMISO Mar 20162020
Onshore wind project G081, Pipestone County
Onshore wind
1.0 MWAgreement signed Pipestone, MNMISO Feb 2001target 2003
Other project J258, Stearns County
Other
1.0 MWAgreement signed Stearns, MNMISO Oct 2012target 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)