United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Maryland (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,731 MW
Active in queue1,731 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn8382 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AH1-552, Prince George's County
Solar + storage Β· Chalk Point Steam, LLC
670 MWIn study Prince George's, MDPJM Mar 2025target 2025
Battery storage project AH1-725, Harford County
Battery storage Β· Cardinal Energy Storage East, LLC
500 MWIn study Harford, MDPJM Apr 2025
CPV Wilson Solar
Solar Β· CPV Wilson Solar, LLC
200 MWIn study Garrett, MDPJM Mar 2025target 2024
Pulaski Energy Storage
Battery storage Β· Pulaski Energy Storage LLC
135 MWIn study Baltimore, MDPJM Feb 2025target 2025
Solar project AG2-618, Charles County
Solar Β· DESRI Tidewater Development, L.L.C.
110 MWIn study Charles, MDPJM Mar 2025target 2023
Solar project AG2-617, Anne Arundel County
Solar Β· Dairy Farm Solar, L.L.C.
55.0 MWIn study Anne Arundel, MDPJM Mar 2025target 2023
Gas project AH1-744, Prince George's County
Gas Β· Parkway Generation Operating LLC
53.5 MWIn study Prince George's, MDPJM Apr 2025
Solar project AH1-057, Wicomico County
Solar Β· Kumquat & Citron Cleantech LLC
7.2 MWIn study Wicomico, MDPJM Mar 2025target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)